News | DrumhellerMail - Page #267
11092024Sat
Last updateMon, 04 Nov 2024 2pm

Redesign of $350,000 realized for Midland berm realignment

Figure1

Drumheller Resiliency and Flood Mitigation Office (DRFMO) has found some potential cost savings through optimizing the alignment of a portion of the Midland berm in North Drumheller by utilizing the old CN Rail embankment.
DRFMO project director Deighen Blakely presented the proposed alignment change to council at the Monday, February 13 Committee of the Whole meeting and noted the new alignment would have cost savings of an estimated $350,000.
“Following receiving the tenders for the Midland flood berm we took a look at the costs for the overall project and, specifically, the leg on the west end of the project that runs parallel to 25 Street NW and ties to higher ground at North Dinosaur Trail (Highway 838),” Ms. Blakely explained during the meeting.
The original design would see a new berm structure some 200 metres in length, and is estimated to cost some $714,800 to build this leg of the Midland berm alone.
She noted using the rail embankment was also considered, especially considering it has withstood numerous floods over more than 100 years. Since the Town of Drumheller signed a 25 year lease agreement with CN Rail to allow the Town to use former rail right of ways for its Rails to Trails network it was wondered if there might be an opportunity to use this embankment.
Although the new alignment will have some additional costs to survey, engineer, and design, it is anticipated there will be cost savings of some $350,000. The rail embankment will also have a top width of approximately 9.5 metres compared to the approved 4 metre top width of other berms.
Councillor Tom Zariski questioned whether CN Rail had been consulted regarding this alignment change, as the land still belongs to CN and the Town is only leasing it.
In a statement to the Mail, Ms. Blakely says,
“...the Town has an agreement in place to use the CN Rail for pathways, which involves work very similar to what we are proposing (for the Midland berm realignment). The Flood Office also has an agreement in place to alter the CN Rail embankment on the originally proposed alignment, by digging into it and replacing the material with clay.”
She adds drawings for the proposed alignment will be circulated to CN Rail once complete, but does not anticipate isues due to these existing agreements.
It was noted this alignment was one of the suggestions council has heard from the community and is an example of how community input is important to the project, though was not necessarily inspired by these conversations.


Monday morning vehicle fire, Highway 10

CarFireweb

 

Rosedale and Drumheller fire halls responded to a single-vehicle fire Monday morning, February 20, just before 10 a.m., on Highway 10 east of Drumheller, near the Hoodoos. There were no apparent injuries reported.

Wheatland County approves budget increase for more bridge repairs

1IMG 5552

Wheatland County council has approved an increase of $335,000 to its 2023 Operating Budget to complete some extensive repairs to several bridges within the county.
Operations manager Cody Zimmerman presented council with the request during the regular Tuesday, February 7 council meeting and explained inspections of six major bridge files within the county’s jurisdiction showed potential rot on five bridges, requiring significant repairs.
“Annually we complete inspections on a portion of bridge files to make sure everything is safe and up to code, and safe for public use,” Mr. Zimmerman shared during the meeting.
Once the rot was identified, additional inspections were conducted but the results were not received until December 2022 after budget deliberations were held, and repair costs were much higher than originally anticipated.
Mr. Zimmerman noted extensive rot was found on multiple bridge elements. This has resulted in a lower rating of the bridge substructure, which has also impacted remaining estimated lifespan of these structures, and require immediate attention for repair.
All five bridges are located in the northern portion of Wheatland County between Range Road 244 and Range Road 222, south of Highway 9 and north of the Village of Rockyford.
“All of these bridges were in the bridge plan for the next five years for replacement, with a total cost of $2 to $3 million per bridge,” Mr. Zimmerman said.
He added it is not recommended to delay repairs as these structures directly affect transportation and public safety. It is estimated the lifespan of these bridges could be extended between nine and 15 years, which would delay the need to replace these structures, if repairs are completed immediately.
Wheatland County council had previously approved a total of $260,000 for engineering and contracted services within its 2023 operating budget for bridge maintenance and repairs. However, with the additional files added the cost of repairs is estimated to be some $330,000 above this previously allocated amount. This includes an approximate additional $33,000 for engineering costs and some $298,000 in contracted services.
Council unanimously approved the increase of $335,000 to complete repairs of these bridge files; this work will be tendered for completion later in the year.


Subcategories

The Drumheller Mail encourages commenting on our stories but due to our harassment policy we must remove any comments that are offensive, or don’t meet the guidelines of our commenting policy.