News | DrumhellerMail - Page #180
11062024Wed
Last updateMon, 04 Nov 2024 2pm

Aquaplex in dire need of repairs

IMG 1337

The indoor pool of the Drumheller Aquaplex was closed to the public due to a suspected leak which was discovered on Monday, July 10; although the indoor pool has been closed, the outdoor pool has remained open, weather dependent.
Infrastructure Services director Dave Brett presented Town council with an update on the status of the Aquaplex during the regular Monday, July 24 council meeting and outlined several issues which have been discovered since the closure.
“This is not going to be a fast repair,” Mr. Brett stated. “There is significant problem and we’ve hit a point where we can’t bandaid it anymore. This is going to take a bit of work to get this done in a way that is safe for the staff to actually function in there.”
The initial issue was in the recirculation pump pit, which has a drywell design, where more than a foot of water was discovered in the structure.
Upon further investigation it was discovered sediment sand and gravel, which is used for the pool filtration system, had buried the sump pumps for the recirculation pump pit. This has resulted in the sump pumps being blocked.
Further to the blockage, the washed out sediment has created a void beneath the mechanical room floor. At this time it is estimated the void is at least 1.5 metres deep.
The erosion of the sediment has also resulted in a lack of support for some buried piping, including the recirculation return pipe. This has resulted in a jam of the recirculation pump and hairnet strainer, which have both been removed.
However, Mr. Brett explained, until the pipe is properly supported, it is undetermined whether these can be reinstalled.
Corrosion of the sanitary pipe was also discovered, though the full extend of the corrosion is not known at this time.
Along with these issues, Mr. Brett also noted there are some pre-existing safety concerns.
The mechanical room is very congested and poses a challenge for most of the Aquaplex staff to work in. There is currently only one staff member who is capable of accessing certain areas of the mechanical room.
Mr. Brett explained the next steps will be to complete a video inspection of the sanitary plumbing system in order to determine the full extent of the corrosion, and consultation with a structural engineer to develop repair options.
He acknowledged the Aquaplex is a cornerstone of recreation for the Drumheller Valley and also serves the local Canadian Badlands Aquatic Club (CBAC), and the impacts the closure has had.
Earlier, during the meeting, council had approved the Parks and Recreation Master Plan which outlined the Aquaplex as having an end of life of approximately 10 years, and Mr. Brett shared three options with council regarding potential next steps-permanent closure of the indoor pool with the outdoor pool open seasonally; repairs; or renovation of the Aquaplex.
Repairs to address the void space, structural weaknesses, and the corroded piping would require the floor of the hallway and lobby, as well as the mechanical room, to be broken up to access necessary components for repair.
At this time the full extent of repairs needed are unknown, and a very early estimate would put repairs at around $750,000.
Mr. Brett stated this will not address the ongoing safety concerns of the mechanical room, and would not fully address some other issues which could pose the potential for the indoor pool to face “end of life events.”
Renovations would help to expand the mechanical room and address space constraint issues, as well as relocate pumps and piping, and see the pump wells resized.
Although this would help address some of the ongoing safety and reliability issues, this would use a significant portion of public funding for a facility which is nearing the end of its usable life cycle. Mr. Brett noted the full budget for renovation work is unknown at this time, but an early estimate would put the renovation between $1 to $2 million.
He explained to build a full new aquatic recreation facility would cost some $30 million and could take several years to complete.
Mr. Brett anticipates further investigations could be completed within a two week period, and a more fulsome estimate for both repair and renovations brought forward for council consideration at a future council meeting.


Drumheller evaluates building market residential, commercial real estate

Copy of Copy of 20170815 Darryl Drohomerski CAO 0412

Town of Drumheller approved its Housing Strategy in April of this year, and one of the goals outlined in the document was the need to develop more residential housing units to support a growing community.
In order to encourage development, council directed administration during the regular Monday, July 10 council meeting to evaluate becoming a builder of residential real estate.
“We have set a goal within our Drumheller Housing Strategy… to build 20 units per year; we are not achieving that right now,” explained Economic Development manager Reg Johnston during the July 10 council meeting.
He shared, although there is some development occurring locally, it is not enough to satisfy this goal.
It was also noted some employers in the immediate and surrounding areas are struggling to find employees due to the lack of “suitable” and affordable housing.
One way the Town has been trying to incentivize residential development is through making improvements to its Residential Incentive Program. The program offers a tax abatement on new developments over a four year period, equal to about two per cent of the construction costs. Some challenges to new development includes increased costs for construction following the COVID-19 pandemic, and increased interest rates, though Mr. Johnston noted these are both at a national level, along with high contractor costs at a local level.
As part of developing this program, administration undertook engagement with real estate brokers and developers and determined, although the program was helpful, it was “not enough to make a difference.”
“When we asked the developers what would work, many of them came back with recommendations of doing joint ventures and partnerships with the Town,” Mr. Johnston explained. “We are open to doing that as well; we recognize we have an advantage with respect to owning property and having the ability to borrow.”
If the Town were to have more involvement with the development process and enter into a joint venture or partnership with developers, units built could be rented out if they did not sell at an approved profit margin. This could also benefit the community due to the low vacancy rate, which Mr. Johnston explained is currently “around zero per cent.”
During discussions, council noted there is also low vacancy rates for commercial real estate and directed administration to evaluate building both residential and commercial real estate; this item will be brought back to council for decision at a future meeting.

Inmate sentenced for assault

Drumheller Institution

An inmate who was serving at the Drumheller Institution was sentenced to 10 months consecutive to his current sentence for his part in a large-scale altercation in July of 2021.
Daniel Loscombe appeared via closed circuit television in the Alberta Court of Justice in Drumheller on Friday, July 14. He pleaded guilty to assault.
On July 20, 2021, RCMP received a call of a large-scale altercation at the Drumheller Institution during recreation time between two rival gangs. This incident resulted in four inmates with stabbing injuries being transported to outside medical facilities.
No staff were injured in resolving the incident.
The incident was investigated by the RCMP with assistance from Correction Services of Canada. The investigation resulted in 10 inmates being charged following the altercation.
Loscombe admitted, during a conversation with another inmate, he struck the individual, which started the riot.
Justice Barley accepted a joint submission from the crown and defence for a 10 month sentence, consecutive to the sentence he is currently serving.


Subcategories

The Drumheller Mail encourages commenting on our stories but due to our harassment policy we must remove any comments that are offensive, or don’t meet the guidelines of our commenting policy.