News | DrumhellerMail - Page #434
11182024Mon
Last updateThu, 14 Nov 2024 9pm

Mayor Colberg, CAO Drohomerski lobby province for additional funding

Drumheller Council CAO

The Town of Drumheller is lobbying the provincial government for additional funding due to escalating costs for projects, including flood mitigation.
Drumheller Mayor Heather Colberg and Chief Administrative Officer (CAO) Darryl Drohomerski met with Alberta Environment and Parks Minister Jason Nixon, Agriculture and Forestry Minister and Associate Minister of Rural Economic Development Nate Horner, and Minister of Transportation Rajan Sawhney on Wednesday, May 25 to request additional funding and provide an update on the flood mitigation project.
“We’re asking for funding to make sure we can finish the current berms part of the original grant request (Midland, Newcastle, Willow Estates, and Grove Plaza), and new berms to protect additional communities,” Mayor Colberg told the Mail.
Drumheller council voted during the May 9 regular council meeting to cancel the tender for the Downtown Dike Phase 1 project after receiving two bids which both came in well over the budgeted amount of $1.4 million for this portion of the project.
CAO Drohomerski added funding approvals were based on 2015 to 2016 costs, with some inflation considered. However, the COVID-19 pandemic presented an unprecedented economic pressure that has seen costs for everything from materials to fuel escalate, and which could not be conceptualized at the time the funding was approved.
Another factor that has increased construction costs for the project was the designed flow rate being increased by the province from 1,640 cubic meters per second (cm/s) to 1,850 cm/s.
This has contributed to the original conceptual berm designs needing to be adjusted to accommodate the additional flow, with freeboard, and to provide protection to additional areas which would otherwise be left without protection based on the new flow rates.
Mayor Colberg says berm sizes are currently being reevaluated to reduce the top width and freeboard amounts to help further extend currently available funding.
She adds a request for decision will be brought before council during the regular Monday, June 6 council meeting (see Council Notes on Page 4).
Along with the request for additional funding for the flood mitigation project, Mayor Colberg and CAO Drohomerski also discussed funding support for the Drumheller Municipal Airport lighting project, which also saw tender bids come in well over budget, improvements to the Hoodoo parking lot, and land negotiation resolutions to complete work to repair the Starmine suspension bridge.


Wheatland County funds 43 community enhancement projects, over $495,000

image001

Wheatland County council unanimously approved to provide nearly half a million dollars in funding support to 43 projects through the Community Enhancement Reserve during the regular Tuesday, May 17 council meeting.
The Wheatland Community Enhancement Regional Board (CERB) received a total of 46 applications from various non-profit organizations throughout the county, primarily focusing on operating funding support.
“This program began in 2012-10 years ago-and to date has contributed $4,476,835.55 for the enhancement and betterment of Wheatland County,” CERB Chairperson Marcy Field explained during the meeting.
Ms. Field noted CERB board members met twice via Zoom in March and April to review the applications. The total funding request of these applications came to $547,803.
It was recommended that Wheatland County council approve 43 of the applications, amounting to $495,469.46, and decline three applications.
Division 1 Councillor Shannon Laprise questioned why some of the applications, such as the Hussar and District Agricultural Society which had requested a total of $100,000 in grant funding, were significantly higher than others.
Ms. Field explained some funding requests were calculated on projected operation costs for the year based on current expenses. Actual costs are required to be submitted at the end of the year and, if there are any discrepancies, any remaining grant funding must be returned.
Council unanimously approved the request to support the recommended 43 applications.

No increase for Big Valley taxes

BigValley 2021

Big Valley council has approved its 2022 Operating and Capital budgets and have managed to maintain zero increase for its municipal tax rate following the regular Thursday, May 19 council meeting.
Although the 2022 budgets were passed during the April 21 council meeting, amendments were brought back for council consideration and approval to avoid potential budgetary deficits.
“The operating budget amendment was necessary because revenues had been overstated in the original budget that was passed, and had to be amended so we didn’t end up with a potential deficit,” Chief Administrative Officer (CAO) Elaine Macdonald explained.
Council passed the operating budget in the amount of $654,115 and a capital budget of $140,000.
CAO Macdonald notes, despite the amendments to the Operating budget, this will not impact the zero increase to the municipal tax rate, and village residents will also see no increase to their municipal water service fees.
Council also authorized the use of $15,342 in Municipal Operating Support Transfer (MOST) funds to help balance the 2022 Operating budget. Municipalities across Alberta received provincial funding in 2020 to help offset additional operating costs due to the COVID-19 pandemic, which included provisions for lost revenues.


Subcategories

The Drumheller Mail encourages commenting on our stories but due to our harassment policy we must remove any comments that are offensive, or don’t meet the guidelines of our commenting policy.