News | DrumhellerMail - Page #376
09272024Fri
Last updateSat, 21 Sep 2024 12pm

Town of Drumheller awards four berm project contracts

IMG 0088

Town of Drumheller council awarded four contracts for construction on the Newcastle, Midland, Willow Estates, and North Drumheller Grove Plaza berms during the regular council meeting on Tuesday, August 2.
In June, council cancelled tenders for the Downtown Dike project due to costs for the project increasing beyond the previously approved amounts, and a full project redesign was recommended to reduce the top width of other berm projects–from six metres down to 4.5 metres, as well as reducing freeboard–to help reduce costs
Construction on the Newcastle Berm is expected to begin in mid-September with completion estimated for the end of November and is not anticipated to interfere with activities at the Newcastle baseball diamonds, including a tournament over the September long weekend.
A total of three bids were received from Pidherney’s Inc, Kichton Contracting Ltd, and Wilco Contractors Southwest Inc, ranging from $2,269,114.16 to $2,989,750.
It was recommended to award the contract to Pidherney’s Inc who submitted the lowest bid.
Flood Mitigation Program project director Deighen Blakely explained an engineering pre-tender estimate had been conducted for all four of the projects. With the exception of the North Drumheller Grove Plaza project, all the tender bids were found to be in line with the pre-tender estimate.
Ms. Blakely noted while the North Drumheller bid from Wilco Contractors Southwest Inc came in about $131,000 over the pre-tender estimate of $645,640 it was determined the bid was comparable against other submitted tenders.
As Wilco Contractors were the only bid for this project, at $786,350, it was recommended to award them the contract.
This project is anticipated to take approximately eight weeks to complete and is expected to be finished by early November. There is an estimated cost savings of 15 per cent following design revisions.
Three bids were received for the Midland berm tender from Wilco Contractors, Pidherney’s, and Kichton Contracting. This project is expected to begin mid-August and is anticipated to take about 16 weeks to complete.
It was recommended the contract be awarded to Wilco Contractors, who submitted the lowest bid amount at a total tender amount of $3,786,125.
Ms. Blakely explained construction along this portion of the project will restrict access to the existing trail systems in this area for the duration of construction.
She also noted there is an estimated cost savings of 10 per cent for this project.
A total of two bids, from Wilco Contractors and Kichton Contracting, were received on the Willow Estates berm project.
There is currently no overall flood protection in the Willow Estates community, and the community would be susceptible to flooding in the event of a flood event at the 1,850 cubic metre per second (cms) level of protection determined by the province.
Due to the amount of work needed to build the berm, and place riprap for erosion protection, this project is expected to take the longest at an estimated 20 weeks.
Despite the lengthy construction time required, it is estimated construction will be complete by the end of 2022.
It was recommended to award the contract to Wilco Contractors for the amount of $2,950,925.
Although council voiced concern over Wilco Contractors’ ability to complete the three projects on time, Ms. Blakely noted they had bid on all four and had hoped to be awarded all four contracts.
Council unanimously awarded the Newcastle project to Pidherney’s Inc, and the remaining three contracts to Wilco Contractors.


Kneehill County drafts letter to MPs over rural economic development concerns

Kneehill County Council

Conservative Members of Parliament Damien Kurek, Shannon Stubbs, and Jacques Gourde have reached out to rural municipalities, including Kneehill County, to inquire about issues the region faces for rural economic development.
The MPs believe the amount of support received from the federal government by municipalities with populations under 20,000 residents is unfair when municipalities with larger populations receive more support.
“They (the MPs) are asking what the top three areas where we can use assistance on, or where the whole of government can focus on to better help rural areas develop,” Kneehill County Chief Administrative Officer (CAO) Mike Haugen explained during the June 21 Committee meeting.
Kneehill County council discussed at length what they felt were the top three issues during the June 21 Committee of the Whole meeting, and the request was brought back at the regular Tuesday, June 28 council meeting for council direction.
Access to reliable high-speed internet, supports for labour including housing, social supports, education, and medical, and overall increasing business costs were brought forward by the committee as the top three concerns.
“When you’re looking at, even Three Hills with a population of 3,500--or whatever it happens to be--funding is going to go to Red Deer with 100,000 or more, and does not come to a place like Three Hills, or Trochu or Acme,” Deputy Reeve Ken King shared during the committee meeting.
Council unanimously directed administration to draft the letter to MPs Kurek, Stubbs, and Gourde outlining the top three concerns for economic development in Kneehill County.

Hussar council to consider backyard chicken bylaw

chicken 874512 1920

Hussar village council has directed administration to draft a Backyard Chickens bylaw for first reading consideration following the regular Thursday, June 30 council meeting.
A resident first brought forward a proposal to keep backyard chickens to the regular June 8 council meeting, citing a recently passed Backyard Chickens bylaw from the Town of Strathmore.
Since the June 8 meeting, administration and council have received emails and a letter in support of the proposal.
Several benefits were listed in the proposal. This included giving children in the village an opportunity to participate in 4-H Clubs with a poultry program, increasing sustainability for residents by collecting eggs and having a means to reduce garbage through feeding backyard chickens garden scraps, as well as controlling bugs and providing natural pest control.
Among the provisions considered in the proposed bylaw are the number of laying hens permitted per residential property, minimum coop or run sizes, and license fees.
The Backyard Chickens bylaw will come back before council for first reading consideration at a future council meeting.


Subcategories

The Drumheller Mail encourages commenting on our stories but due to our harassment policy we must remove any comments that are offensive, or don’t meet the guidelines of our commenting policy.